- Builder – Evans Harch
- Project Value – $1.9 million
- Duration – 12 months
Project Overview:
New construction of Gold Coast City Council’s community centre consisting of Library, Community Meeting Rooms and Auditorium as well as new Pool facilities and car parking.
Project Scope:
- Supply Authority Transformer
- Underground conduit and pit systems
- Carpark Lighting
- Main Switchboard (1200Amps)
- Sub-mains and Distribution Switchboards
- General Light and Power
- Dynalite Lighting Automation
- Nexus Emergency Lighting System
- Cat6 Systimax Telecommunication installation
- Tecom Challenger Security and Access Control System
- IP CCTV System
- 14kW Photo Voltaic (Solar) System